Cement Creek (Ross Basin)
September 10-21, 1999
Study Design & Sequence of Events
Study Design
The objective of the study was to determine the principal sources of metals
and acidity in the upper reaches of Cement Creek, upstream of Gladstone.
The injection site was located below Ross Basin and above the Mogul Mine.
Synoptic samples were collected at various locations, starting just below
the South Fork and continuing upstream to the injection site.
Sequence of Events
| September |
| 10-11 |
Stream measurement and reconnaissance |
| 19 |
Tracer injection begins at 1639 hours |
| 20 |
Water quality sampling for synoptic study |
Photo Gallery
Synoptic Sites
Key
| str | - stream site
|
| rbi | - right bank
inflow |
| lbi | - left bank
inflow |
| con | - confluence
|
| +++ | - downstream
from designated site |
| --- | - upstream
from designated site |
Results & Acknowledgments
Results
Data analysis is incomplete at this time.
Acknowledgments
The Ross Basin synoptic was done in cooperation with
the U.S. Bureau of Land Management. Field assistance was
provided by Dana Bove, Ken Leib, Mary Leib, Suzanne Paschke,
Bruce Stover, Phil Verplanck, and members of the